Barge segments headed for Wolford Mountain Reservoir

0
1112
Barge segments that will be assembled this spring at Wolford Mountain Reservoir into a platform similar to this willstart showing up in the day-use parking lot at the reservoir. The platform will be used to stage a crane and operations for divers that will replace the main outlet gate at the reservoir. The pictured operation took place at Steamboat Lake.
Barge segments that will be assembled this spring at Wolford Mountain Reservoir into a platform similar to this willstart showing up in the day-use parking lot at the reservoir. The platform will be used to stage a crane and operations for divers that will replace the main outlet gate at the reservoir. The pictured operation took place at Steamboat Lake.

Preparing for springtime replacement of main outlet gate

This spring, the Colorado River District will replace the main outlet gate at the Wolford Mountain Reservoir dam. At its January 16, 2019 Board meeting, Colorado River District Directors approved a $444,000 contract with Marine Diving Solutions LLC of Centennial, Colo. to take out the old gate and install a new stainless steel one purchased previously by the District and being fabricated in Massachusetts.

A large, floating work platform will be assembled to hold a crane, divers’ decompression chamber, work trailer, diving equipment and the gates as they are removed and installed. The work platform will be assembled near the boat ramp from the 8- by 10- by 40-foot segments when the reservoir is ice free and towed to the outlet tower.

The main gate is in 100 feet of water when the reservoir is drawn down. This work needs to be completed in early spring to take advantage of the shallower reservoir depth. Once the existing 17,000-pound gate is removed the new gate will be installed and tested.

The work platform segments and other equipment are coming off another Colorado reservoir project and will begin showing up in the south end of the reservoir’s day use parking lot near the boat ramp. The project is expected to take five weeks once the work platform is assembled and be completed near mid-May. The majority of the day use parking lot will be available for public use and the dam crest open for foot traffic during the project.

A large, floating work platform will be assembled to hold a crane, divers’ decompression chamber, work trailer, diving equipment and the gates as they are removed and installed. The work platform will be assembled near the boat ramp from the 8- by 10- by 40-foot segments when the reservoir is ice free and towed to the outlet tower.

The main gate is in 100 feet of water when the reservoir is drawn down. This work needs to be completed in early spring to take advantage of the shallower reservoir depth. Once the existing 17,000-pound gate is removed the new gate will be installed and tested.

The work platform segments and other equipment are coming off another Colorado reservoir project and will begin showing up in the south end of the reservoir’s day use parking lot near the boat ramp. The project is expected to take five weeks once the work platform is assembled and be completed near mid-May. The majority of the day use parking lot will be available for public use and the dam crest open for foot traffic during the project.